MAY - 2024

Steel Structure Work shop and associated civil works,Electrical and Drainage works and installation of overhead crane 5.0 Ton at Al – Yousfi Work shop at Mina Abdullaha.

APRIL - 2024

Supply and Installation of site facilities and Overhead crane erecting for CMS North Kuwait yard. ·Project Title -Supply, installation, surveillance and maintenance of sucker rod pumping system (SRP) work including, yard asphalting, perimeter closed Kirby PE Building, Office cabin, Security cabin, car shed, Asphalt road work, Fire fighting ,Plumping ,sewage and Electrical works.

NOVEMBER - 2023

Supply and installation of Illuminated Signage boards for KIPIC – MINA AL-ZOOR Project.

OCTOBER - 2023

Supply, Fabrication, Erection of Sandwich panel type Cylinder enclosure Size 4.5 Mtr Length x 3.0 Mtr Width x3.0 Mtr Height. Including design support for fabrication and civil works. for KNPC Mina Ahmadi.CLIENT- GULF SAFETY SABHAN

SEPTEMBER - 2023

Install 80 LED light fixtures at 2.9 mtr height with cable tray and DB at MED Warehouse CLIENT- ENGIE Solutions.

AUGUST - 2023

Replacement of Light fitting at ZAIN HQ2 820 Water proof LED fittings with conduit and cable.CLIENT- ENGIE Solutions.

AUGUST - 2023

Supply and installation of LED lighting at AZN ware house and power plant at Mina-Al Zoor 654 nos with conduits,wires control switches,DB and exit lamps.CLIENT- ENGIE Solutions.

AUGUST - 2023

Dismantling the existing chain link fence and supply and install new PVC coated chain link fence height 1.5 Mtr, wire thickness 3.76 mm MPW approved wire qty. 528 mtr with associated civil works and lighting on the fence pole at GE work shop Sulibiya.CLIENT- ENGIE Solutions.

JUNE - 2023

Supply and install illuminated signage for UNITED GULF EXCHANGE COMPANY -JAHARA BRANCH.

JUNE - 2023

Supply and install illuminated signage for BURGER STREET SALMIYA.

MAY 2023

Supply and installation of bollards barrier post special high strength plastic tube with reflective red and white color 80 cm height with base plate and chain at GE workshop Sulaibita 124 nos CLIENTENGIG Solutions

APRIL 2023

Survey,Desigin,supply and construction at AMOR SOI Wellnes centre:- Supply & apply waterproofing in the floor ,Supply & install plumbing and drainage lines, Supply & install electrical conduiting, cabling to install sockets ,Supply & install screeding on the entire floor ,Supply & install flooring as shown in 3D using Vitrified Tiles (120 X 60),Supply & install 3mm MDF sheets,Supply & install partition using waterproof gypsum board,Supply & install ceiling using waterproof gypsum board, Supply & apply 2 coats of Majoun, 2 coats of primer and 2 coats of Antibacterial Fenamastic Semi Gloss White paint,Wall cladding & Carpentery Works.Supply & install artificial marble, Supply & install checkered Belgium mirror using two-part adhesives (Urethane and Silicone),Supply & install hidden flushed doors using artificial marble and teak wood veneer for the 4 elevators.Supply & install LED profile lights, flush with walls,Supply & install Dimmer switches. Supply & install Black Cylinder lights (Firefly/NVC or equivalent) in the Ceiling light grooves. Supply & install LED strip light,Supply & install Skylight using Fibre optic cables,Supply & install warm white track lights (Firefly/NVC or equivalent.Bathroom & Sanitary works – Supply & install flooring & wall tiles as shown in 3D using Vitrified Tiles 60 X 30),Supply & Install Massage Jacuzzi Bathtub with mixer faucet.Supply & install plumbing & drainage line in the laundry room to install washing machine and dryer,Furniture & Carpentry-Supply & install Sofas as shown in 3D rendering in the Guest lounge, Counselling lounge, Corridor, Reception and other rooms, Supply & install Vertical blinds for all the windows,Supply & install Coffee tables,upply & install corner cabinets,Supply & install workstation with overhead cabinets,Supply & install Reception Table,Supply & install branding signage behind the Reception table ,upply & install wooden doors for all the rooms,Supply & install 10mm tempered glass partition with doors for the massage rooms,Examination cum Treatment bed for all room,Supply & install open storage shelves in the store room,HVAC- Give additional supply with separate thermostat to the server room.,Modify existing ducting for the new layout. Recessed linear diffusers to be installed. Seperate thermostat, dampers and controls,Supply & install ceiling exhaust fans for all bathrooms and laundry rooms.ENTERTAINMENT & SECURITY– Supply & install Ceiling speakers (Bose Professional FreeSpace FS FS4CE) in all the rooms and corridors and foyers. Necessary cabling has to be done to the console position in the backoffice. Amplifier (Yamaha) also to be provided. Each room should’ve remote control to control the speakers.Supply & installation of CCTV 8 MP 4K image sensor dome camera DS-2CD2183G2-I=14 Nos. with 24” Monitor for IT room. 32 Channel NVR with 8HDD support DS-9632NI-18=1Nos. (120 days video recording). Hikvision 24 Port PoE switch=1 Nos. WD 8 TB HDD Purple=6 Nos. ACCESS CONTROL SYSTEM: Hikvision Access Terminal DS-K1T343EFX=37 Nos. Hikvision Magnetic Lock DS-K4H250S=37 Nos. Push button (No touch)=37 nos, TIME ATTENDANCE SYSTEM: ZKT IFACE880 multi biometric time attendance=1 No. NETWORKING:
1) 42u server rack cabinet with pdu and cooling fans=1 Nos,2) 24 port patch panel =6 Nos,3) 24 port PoE switch=6 Nos,4) Aruba Wifi access points =7 Nos,5) Network points=56 Nos FULL HD DISPLAY POINTS: 1) Full hd display out put with hdmi=18 Nos
2) 12 port Full hd hdmi splitter=1 Nos CEO ROOM – Supply & install wall cladding in the CEO/Board room using artificial marble and MDF CNC,Supply & install CEO desk (1.6M x 80 Cms) using Artifical marble and Bronze color GI pipes ,Supply & install round meeting table (1 M diameter) using Artificial marble and Metal legs ,Supply & install guest chair,YOGA/GYM– Supply & install Brick wall cladding on the walls of Yoga and Gym and Supply & install flower bed.

MARCH-2023

Supply and installation of bollards.barrier post special high strength plastic tube with reflective red and white color 80 cm height with base plate and chain at GE workshop Sulaibita 124 nos. CLIENT- ENGIE Solutions

MARCH-2023

Supply and construction of Asphalt road works at SAUDI ARABIAN CHEVRON facility – Mina Al Zour. including Removal of existing Asphalt. 1860 SQM. Supply and preparation of sub base layer Milling, Gatch and Aggregate Mix. (1:1:1),Supply and apply Asphalt Type 0I of thickness 8 cm .with Prime coat,Supply and apply Asphalt Type III of thickness 4 cm .with Tack coat. (Anti stripping) and Supply and apply Road marking White 20 cm. CLIENT- BADER AL-MULLA.

MARCH - 2023

installation of copper pipe,fit-up,welding,rack installation insertion of rubber foam insulation,fostering,copper pipe by-pass,indoor unit connection,G.I conducting and wiring,pressure testing ,flushing and installation of HVAC Outdoor and Indoor Units for PUBLIC AUTHORITY FOR HOUSING WELFARE 40 RESIDENTIAL PROTOTYPE TOWERS, SABAH-AL-AHAMED CITY. CLIENT- UNITED BUILDING COMPANY.

MARCH - 2023

Supply and install illiumanated Sigianage for KIPIC Mina Al- Zoor.

MARCH - 2023

Supply and install pre-cast concrete Barrier 3 Mtr length x 0.81 mtr height x 0.6 mttr width as per MPW standard and specification 3600 nos , at SAUDI ARABIAN CHEVRON facility – Mina Al Zour. CLIENT- BADER AL-MULLA.

FEBRUARY - 2023

pre-fabricated Toilet unit for New Site-with all plumbing ,drainagelines and electrical works for DAN TRADING AND CONTRACTING CO.W.L.L.

JANUARY - 2023

Construction and Installation of site facilities for CMS Wafra yard (Inside KDC YARD) ·Project Title -Supply, installation, surveillance and maintenance of sucker rod pumpingsystem (SRP) work including, yard asphalting, perimeter closed Kirby sheet fencing, equipment erection and workshop.

JULY-2022

Supply and install illuminated signage for PAPA KANAFA ARDIYA, Al-Rai, Kuwait.

JUNE-2022

Supply and install illuminated signage for YESSAYAN JEWELARY The Avenues Mall, Ghazali St, Al-Rai, Kuwait.

FEBRUARY-2022

Supply and Installation Eagle Eye Bird Control wind driven.t SAUDI ARABIAN CHEVRON facility –Mina Al Zour. CLIENT- BADER AL-MULLA.

FEBRUARY-2022

MANUAL EXCAVATION UPTO 4m- DEPTH : Qty.5000 CUM Mobilization, marking Site, clearing work Site, preparing right of way, excavation by hand held tools, up to 4.0 mtr depth for any works. Perform backfill with manual compaction using hand rammer with approved soil and compaction, clear the work area, and remove all debris to designated municipal area. As per CHEVRON engineering standards at SAC facilitates Mina al zoor. CLIENT- BADER AL-MULLA.

DECEMBER-2021

Machine Excavation 15000 CUM-Mobilization, marking Site, clearing work Site, preparing right of way, excavation by Machine, up to 4.0 mtr depth for any works. Perform backfill with manual compaction using hand rammer with approved soil and compaction, clear the work area, and remove all debris to designated municipal area. As per CHEVRON engineering standards at SAC facilitates Mina al Zoor. CLIENT- BADER AL-MULLA.

OCTOBER-2021

Rectification of Blast Proof Door Internal Mechanisam -Mechanical Repair Work, Erection ,Rigging, Fit-up, Hot Work, Cold Work .Complete repair and restoration of the door to normal functionality for 27 Doors. at MOB1 – CLEAN FUEL PROJECT KNPC CLIENT-Energy and Environment Co., for Gen Trading & Contracting W.L.L.

MAY-2021

Supply and install illuminated signage for HOME GARDEN Nursery Al-rai,Fourth Ring Road Kuwait.

JULY-2020

Rectification of Blast Proof Door Internal Mechanisam -Mechanical Repair Work, Erection ,Rigging, Fit-up, Hot Work, Cold Work .Complete repair and restoration of the door to normal functionality for 32 Doors. at MOB1 – CLEAN FUEL PROJECT KNPC CLIENT-Energy and Environment Co., for Gen Trading & Contracting W.L.L.

JANUARY-2020

installation of copper pipe,fit-up,welding,rack installation insertion of rubber foam insulation,fostering,copper pipe by-pass,indoor unit connection,G.I conducting and wiring,pressure testing ,flushing and installation of HVAC Outdoor and Indoor Units for PUBLIC AUTHORITY FOR HOUSING WELFARE 40 RESIDENTIAL PROTOTYPE TOWERS, SABAH-AL-AHAMED CITY. CLIENT- AWAH INT.GROUP.

DECEMBER - 2019

Supply and Install Automated sliding gate 8.8 Mtr ,Single leaf sliding gate.13.1 mtr,steel grill for the boundry wall 26 Mtr and steel manuel door 2 nos 2.3 mtr Length. At Khiran for AL- Sabha Villa.

NOVEMBER - 2019

Supplyand Install ,Interlocking,Kerbstone ,Boundry wall and associated Civil and structurel works at Messilah beach for Her Excellency SHEIKHA MUNEERA AL -SABAH .

OCTOBER-2019

Survey, design, supply, fabrication, delivery, erection and construction Works of two (2)numbers Portal cabins with approach and service roads, production well, discharge well and RO unit, Chain link fence 10 KM and crash barriers 10 KM using Steel pipes 3” for the Natural Sanctuary at Al-Qurain in Wafra, complete with the all necessary electrical including diesel generator and diesel tank, HVAC and fire fighting Works CLIENT – HALLY TRADING & CONT.CO.

AUGUST - 2019

Supply and install illuminated signage for OPPLE LED products Road sign in front of their store in Ghazali street AL-Rai Kuwait.

JUNE-2019

Cable Tray Installation work – New Gathering Center 31,KOC North Kuwait Field – Client- DODSAL Company. And ROMETCO GTC. Kuwait.

MAY - 2019

Commercial complex , Salmiya Block No 8, Building No.158. Multi story building ,including footing, reinforced concrete in building and equipment foundation, ground beams, and slab on grade including reinforcement formwork. apply 2 coats of rubberized water proofing paint around surfaces of R.C. Elements underground (footing, column ·neck, GB etc.) block and brick work, aluminum works, Ceramic wall & floortiles works,·plaster and paintworks, Adhesive and Grouting works, Drainage all electrical, Plumbing,HVAC Septic Tanks, Soak Pits, Manholes, Gully Traps, floor traps and all necessary piping for drainage and sewage Works etc.,

MAY - 2019

Supply and install signage for global retailer WIBI Kuwait.

APRIL - 2019

Fire-fighting HDPE line at GC 16 & GC 28 (Gas compression & Re-injection Facility) CLIENT- SPETCO INT.PETROLEUM COMPANY.

APRIL - 2019

Trench work in Shuwaikh Port in side JTC garrage – supply,Fabrication,excavation and RCC works Length12 Mtr x Width 1.0 Mtr x 2.0 Mtr Depth.

MARCH-2019

Micro Tunneling works at Eagella SE -69. Grouting ,sleeving and tunneling works to ·insert 1200 mm water Ductaile (Kubota) pipe line in to 1400 mm Sleeve total length 1(one) KM CLIENT – HALLY TRADING & CONT.CO.

FEBRUARY - 2019

Removal of the old sewage under ground Tank 10,000 gallon from Kuwait Port – client- JTC and install new Steel sewage Under ground Tank 10,000 gallon with concrete pad at the bottom and top,4 side concrete wall, Manhole,Air vent and under ground pipe line connection.

FEBRUARY-2019

Research Work shop building (Multi Story) in Kuwait Institute of Scientific Research ,Center (KISR) Shuwaikh. Construction of one Multi story building including footing, reinforced concrete using sulphate-resisting cement in building and equipment , foundation, ground beams, and slab on grade including reinforcement formwork . apply2 coats of rubberized water proofing paint around surfaces of R.C. Elements ,underground (footing, column neck, GB etc.) block and brick work, aluminum works, Ceramic wall tiles works, Ceramic floor tiles works, plaster and paintworks, Adhesive,and Grouting works, Drainage all electrical, Plumbing, HVAC Septic Tanks, Soak Pits, Manholes, Gully Traps, floor traps and all necessary piping for drainage and sewage.Asphalt and road work including Kerb stone and Inter locking tiles. Road marking paint. Car Parking shelter, Cladding works interior decoration Works etc.,CLIENT – HALLY TRADING & CONT.CO.

FEBRUARY - 2019

Fuel oil Pipe Line from Mina Al Ahamadi Refinery to Doha West Power Station. Contract No. MOE-EW/3466/2006-7 (Fabrication,welding and Tie in works of 20 Inch Pipe line) 42 KM. Sub contract with M/s.Nowan Construction South Korea.-CLIENT- EPTS AHAMADI.

DECEMBER - 2018

Construction,Installation,Testing,Assist Tab works and commissioning of external chilled water pipe line works in Sheikh Salem Ali-Al-Sabah Camp.(Former KAZMA Camp) Client- Ahmadiah Contracting & Trading Co.

DECEMBER 2018

Car parking Sheds in Shuwaikh and Adhieliya area. Including Asphalt work, footing concrete for beams road work including Kerb stone and Inter locking tiles. Road marking,paint. 7000 M2 of Kirby works and 5000 M2 of Asphalt works. 10,000 M2 of Fabric ·Shelter car park.,CLIENT – HALLY TRADING & CONT.CO.

DECEMBER-2018

Office Iinterior Decoration work and partition including Electrical works,Plumbing works,cermic floor tile and wall tile fixing,Gypsum board works, paintig ,Fire system with alarm and dectectors. at Ahmadi for M/s : ARABIENNERTECH.

APRIL-2018

Infra Structure temporary facilitities at Kuwait International Airport New Terminal Building Client- Limak Insat S.P.C